Milestones
MS 1: 15.01.2008 - Delivery and acceptance of remodelled cargo vessel
MS 2: 30.04.2008 - Acceptance of the towing kite system and WaMoS II by the
classification society (GL) and the government safety
organisation
MS 3: 30.01.2009 - Report of intermediate results on energy savings and
greenhouse gas reduction
MS 4: 31.12.2007 - Mid Term report
MS 5: 31.12.2009 - Final report